S6.27 27-0119 Subject: EPA San Francisco Bay Program Grant
From: Oakland Public Works Department
Recommendation: Adopt?A?Resolution Authorizing?(1) The?City Administrator To Accept And Appropriate Grant Funds?In?An?Amount Not?To?Exceed Three?Million?Dollars ($3,000,000) From?The?U.S. Environmental Protection Agency (EPA) San Francisco Bay Program?For?PCB Remediation In Arroyo Viejo Creek; And (2) Adopting Appropriate California Environmental Quality Act Findings
I support item S6.27 (27-0119), accepting the $3M EPA grant for PCB cleanup in Arroyo Viejo Creek, and I support passing it on consent. I ask that staff clarify four points for the record.
1. Match source. The resolution (pp.1-2) says the $1M match comes "from City funds from the Monsanto Settlement," but staff report Table 2 (p.5) shows $200,000 from the Monsanto Settlement and $800,000 from the City Facilities Fund (4400). Which is correct?
2. Union Pacific agreement. The report (p.2) says the 50/50 cost-sharing agreement with Union Pacific is "currently in development." When is it expected?
3. Cost overruns. The project cost is a "maximum estimated" $8M with a City share of $4M (report p.3), but nothing says what happens if costs run higher. Is the City's share capped?
4. Schedule. The Water Board order's deadlines (remedy by Dec 31, 2023; completion report by May 1, 2024) have passed, and the packet gives no new dates. What is the current schedule?
Dear Council Members,
I support item S6.27 (27-0119), accepting the $3M EPA grant for PCB cleanup in Arroyo Viejo Creek, and I support passing it on consent. I ask that staff clarify four points for the record.
1. Match source. The resolution (pp.1-2) says the $1M match comes "from City funds from the Monsanto Settlement," but staff report Table 2 (p.5) shows $200,000 from the Monsanto Settlement and $800,000 from the City Facilities Fund (4400). Which is correct?
2. Union Pacific agreement. The report (p.2) says the 50/50 cost-sharing agreement with Union Pacific is "currently in development." When is it expected?
3. Cost overruns. The project cost is a "maximum estimated" $8M with a City share of $4M (report p.3), but nothing says what happens if costs run higher. Is the City's share capped?
4. Schedule. The Water Board order's deadlines (remedy by Dec 31, 2023; completion report by May 1, 2024) have passed, and the packet gives no new dates. What is the current schedule?
Thank you.
Camrinn Hanley, Oakland resident (Montclair Village)