3.19 26-0419 Subject: Adeline Street Bridge Seismic Retrofit Project Construction Phase
From: Department Of Transportation
Recommendation: Adopt The Following Pieces Of Legislation:
1) A Resolution Authorizing The City Administrator To Award A Construction Contract To Bay Line Cutting & Coring Inc. In An Amount Not To Exceed Three Million Three Hundred Thirty-One Thousand One Hundred Forty Four Dollars ($3,331,144); Waiving The Five Percent (5%) Maximum Mobilization Requirement Per Section 9-3.4 Of The Project Specifications; And Adopting Appropriate California Environmental Quality Act Findings; And