The online Comment window has expired

Agenda Item

3.3 20-0701 Subject: 2020 As-Needed Pavement Rehabilitation Services From: Transportation Department Recommendation: Adopt A Resolution Awarding A Construction Contract To 1) Gallagher & Burk, The Lowest Responsive And Responsible Bidder, And Waiving Advertising And Competitive Bidding And Authorizing The City Administrator To Negotiate And Award Construction Contracts To 2) McGuire & Hester 3) Teichert Construction And 4) O.C. Jones & Sons, The Second, Third, And Fourth Lowest Responsive And Responsible Bidders, Provided That All Meet The Contractor's Bid Schedule Of The Lowest Bid of Gallagher & Burk, For As-Needed Pavement Rehabilitation Services In Accord With The Project Plans And Specifications And The Lowest Bid in An Amount Not To Exceed Twelve Million, Six Hundred And Eighty-Six Thousand, Two Hundred Dollars ($12,686,200.00); Each: On The October 20, 2020 City Council Agenda On Consent